Everyone, the Lake Lansing Road at Towar Avenue traffic signal is activated and three-way red flash. The pedestrian push button signal is not complete at this time and will continue.  Reminder for all traffic must come to a complete stop.

 

Lake Lansing Road is open thru traffic with outside lane closures as there is still more roadwork to be completed. 

 

Bus stops have yet to constructed as some bus stops remain closed with the project limits.

 

Paint subcontractor painted a temporary double yellow centerline

 

Subcontractor is still working on drainage and excavating in White’s Park.

 

Contractor still has concrete curb and gutter, sidewalk ramps,  drainage structures , pave top course, and install permanent pavement Markings. Proceed with caution.

 

If you have any questions , feel free to contact me.

 

Thanks, Eric

​

Eric Burns, P. E.

Construction Engineer

Ingham County Road Department

301 Bush Street

Mason, MI 48854

(517) 719-0070

Monday, August 25th - Lake Lansing open to thru traffic, delays may occur

  • Shift to Westbound Lake E. Lansing Rd. lanes

  • Mill and resurface Eastbound E. Lake Lansing Rd.

  • Asphalt approach and ADA ramps at Harkson Dr. and Foxcroft Rd.

  • North/South ADA Ramp at Northgate Dr.

STAGE 3 - approximately Monday, August 28th to approximately Friday, September 8th

  • Shift to Eastbound E. Lake Lansing Rd. lanes

  • Mill and resurface Eastbound E. Lake Lansing Rd.

  • Asphalt approach and ADA Ramps at Rutherford Ave., Porter Ave., Pollard Ave., Gibson Ave., Hardy Ave., and Hart St.

STAGE 4 - approximately Monday, September 11th to approximately Friday, September 29th

LAYOUT OF FINISHED INTERSECTION - E. Lake Lansing Rd., Towar Ave. and Birch Row Dr.